Thanks
By understanding & my thought is as below.
The leaf switches should be L2 switches.
The Spice switches will be L3
There will be a separate POD for the Management & Edge clusters.
The Edge clusters will be running the Edge gateways which will run routing protocol & establish routing with the Spine L3 switches.
Leaf switches will be providing only the L2 functionality.
If case if leaf switches are configured as L3, all the leaf switches will be L3 & there will be multiple paths when the leaf switches expands.
It will be easy & simple to have the spine as L3 rather than having leaf as L3.
The above is my understanding. If any inputs or suggestions please let me know regarding my understanding.