How can I schedule a job with a frequency of every 3 week and it should be friday.

  • 1.  How can I schedule a job with a frequency of every 3 week and it should be friday.

    Posted Mar 30, 2023 09:37 AM

    How can I schedule a job with a frequency of every 3 week and it should be friday. 



  • 2.  RE: How can I schedule a job with a frequency of every 3 week and it should be friday.

    Posted Mar 31, 2023 12:40 AM

    Hi Himanshu,

    you have to create a calendar object and mark/assign the execution days. Then use either a schedule object or periodic execution to start the job.

    regards,
    Peter



    ------------------------------