Subject: [VMware Aria Operations Management Pack for vSphere Replication] regarding the definitions of some words
This is my guess, yes.
Original Message:
Sent: Jul 03, 2024 09:18 PM
From: apple0529
Subject: [VMware Aria Operations Management Pack for vSphere Replication] regarding the definitions of some words
Hi @Antoaneta Genova
Thank you, so do you mean that because collection time interval is set in short time, transferred megabytes doesn't show anything (which is zero)?
Thank you
Original Message:
Sent: Jul 03, 2024 07:55 AM
From: Antoaneta Genova
Subject: [VMware Aria Operations Management Pack for vSphere Replication] regarding the definitions of some words
The site's metric for transferred megabytes should return historical information about the overall transferred bytes for all replication groups in the VC for the specified period (collection time interval bases). I guess that the collection time interval might be the reason you see 0 here.
Regards,
Antoaneta
Original Message:
Sent: Jul 02, 2024 11:57 PM
From: apple0529
Subject: [VMware Aria Operations Management Pack for vSphere Replication] regarding the definitions of some words
Thank you @Antoaneta Genova
I see, thank you so much.
I have a one more question;
in the RPO Violation dashboard, Transferred bytes (vSphere Replication site metrics) shows zero, but in the Replication usage the parts of Last sync duration, Last sync size as well as Lag time show some variations around 14:00.
(I attached 2 schreenshots so I hope you can check both of them.)
What does this change mean?
I don't understand why some variation occured around 14:00 even though there's nothing change in the RPO violation dashboard.
Thank you
Original Message:
Sent: Jul 02, 2024 06:22 AM
From: Antoaneta Genova
Subject: [VMware Aria Operations Management Pack for vSphere Replication] regarding the definitions of some words
Last sync duration metric stands for the total time (in seconds) used for the latest instance of this replication.
Last sync size metric stands for the total MBs transferred for the latest instance of this replication.
Lag time metric stands for the total time (minutes) spent between now (defined in the terms if the collection interval) and the time when the last sync started.
Regards,
Antoaneta
Original Message:
Sent: Jul 01, 2024 09:14 PM
From: apple0529
Subject: [VMware Aria Operations Management Pack for vSphere Replication] regarding the definitions of some words
Hi team,
I would like to ask regarding VMware Aria Operations Management Pack for vSphere Replication.
What does these words mean? Does anyone know the specific definitions?
- Last sync duration
- Last sync size
- Lag time
These are written in the part of "Replication metrics" in this document; https://docs.vmware.com/en/vSphere-Replication/8.7/com.vmware.vsphere.replication-admin.doc/GUID-54DE9E9D-A569-43DB-9F56-E324B228C1C4.html
That would be healpful if anyone knows that means.