The DL380 G7 server is on the HCL for just the 56xx series Xeon's (for CPU's)...
I'd also suggest looking at the Dell R710 and R810 servers for hosts.
Since you were spec'ing just 16GB of RAM per host, I highly suspect that the number of hosts being called for by cap planner is due to that low number. Go to 48GB and chances are, you'll see a good deal less servers being called for. Spec out the 56xx series Xeon's (if not 65xx or 75xx series) and the CPU usage (per host) will also drop due to higher cores per socket count. Increasing the memory to 48GB per host means you'll easily get the same amount as those 15 hosts in just five. Spend the savings from the reduced host count on another host (getting six) and the VMware licnese count to correspond (hope you're going for Enterprise Plus)...
I would HIGHLY suggest going with iSCSI over NFS for the storage protocol. For one thing, you can select (from vCenter) if the vmdk will be thick or thin provisioned. With NFS, that's dictated by the SAN, so 99% chance it's going to be thin only (with 0 chance of going thick).
I've also had excellent results with the EqualLogic PS6000 series SAN (as well as the PS5000 series before that)... At one company we started with the PS5000 series and added another later (adding it to the same group). Not only does it seamlessly increase the storage you have available, it spreads the storage demand across ALL the spindles (from both chassis) giving you a performance increase. You also benefit from the additional NIC counts from each chassis (four active, four standby, changing ports on a one to one bassis)...
Don't just work with the hardware vendors/manufacturers here. Go to a VMware Premier partner to get their take on things. They will have much better real world experiences. You'll get more solid information that way than just trusting what the manufacturers will tell you... I've used GreenPages at two companies so far, and have had excellent results with them both times (actually, with every project we pulled them in for). Give them a shout to see what they can do to help you... I will say that depending on who you've already contacted, hardware prices could get tricky. VAR's will register opportunities (even if you just ask them some base questions) with manufacturers making it impossible for other VAR's to get the same program dollars that the other place now has locked in. You CAN get that changed, but it's not a fast thing (takes a couple of calls/emails and the original VAR might lie and try to keep things locked in on their end). We saw significant savings when we broke off from one (small time) VAR and put everything into GreenPages plate...
VMware VCP4
Consider awarding points for "helpful" and/or "correct" answers.