vCenter

 View Only
Expand all | Collapse all

Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

  • 1.  Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Feb 12, 2022 05:41 PM
      |   view attached

    Hello,

     

    I am trying to deploy a vcenter 7.0.2 appliance. I was able to finish Stage 1 just fine. However on stage 2, the next button is greyed out on step 2 for setting up the Time synchronization mode and SSH Access. I have tried several configurations on this step but still no luck. 

    Can anyone advise on what I should try doing? 



  • 2.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Feb 14, 2022 11:08 AM

    Have you tried Disabling the SSH Access and Setting up the Time synchronization to either "Host" or an NTP server 



  • 3.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Feb 24, 2022 08:48 PM

    I'm in the same boat you are. Have you figured out how to get past this?



  • 4.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Mar 07, 2022 05:22 PM

    Remove FQDN entry and redploy the vCenter, it worked for me



  • 5.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Jun 03, 2022 05:32 AM

    hi

    what do you mean about "delete FQDN entry" ?



  • 6.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted May 23, 2022 03:21 PM

    Try accesing vCenter_IP:5480
    There you can proceed with the step 2.



  • 7.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Jul 28, 2022 02:38 PM

    login to vcenter with https://<your ip>:5480

    Add the DNS Server IP

    * I did - it is working fine.



  • 8.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Oct 16, 2022 11:23 AM

    Greetings,

    Probably you missed the DNS Server IP.



  • 9.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Aug 16, 2023 07:07 PM

    Connect with your browser to the FQDN name, if you specified it during deployment.

    Maybe you must accept self signed SSL certificate.



  • 10.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Dec 28, 2023 05:24 PM

    the firefox next button greyed out, try chrome the next button is working.

    using the chrome brower next button is showing correctly.



  • 11.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Feb 20, 2024 02:11 PM

    Same for me. NEXT button greyed out in Firefox but worked in MS EDGE. Stage 2 of vCenter installation didn't start automatically for me because of network issues. But I managed to login into vCenter (7.0.3) after Stage 1 and start stage 2 manually. However, having a DNS and a reverse DNS (PTR) records for vCenter was the key to get it installed correctly.



  • 12.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Mar 19, 2024 10:19 AM

    I agree that Using Microsoft Edge, button Next is active.
    In Firefox has grayed.

     



  • 13.  RE: Next Button Greyed Out On stage 2 of Step 2 Vcenter Deployment

    Posted Apr 01, 2024 03:37 PM

    For me I missed putting in a DNS as I hadn't set one up yet. Using the IP:5480 method let me put it in and ungrayed the next button.