New UX: Add ETC by tasks assignments

Last activity 04-12-2019 11:08 AM
zaina DIN's profile image
04-12-2019 11:08 AM

Hello, in the current release 15.6, it not possible to edit in the new experience , ETC by ressources assigned to task. And BNPP BDDF wish to have it to complete the workflow of project management. Here you are the workflow of project management:

==> Create a project and fill properties: OK in the new UX

==> Allocate ressource (staff the project): OK in the new UX

==> Create tasks and assign resources to these tasks: OK in the new UX

==> Add global ETC to task level: OK in the new UX

==> Divide by resource ETC of tasks: KO in the new UX

 

eg: Task conception: 30 hours of ETC

                    Resource A: 15 hours of ETC

                     Resource B: 15 hours of ETC

                     

This is not possible actually.

 

Thanks you.

 

Bests regards.

 