  • 1.  APPLEND Workload Object in D Series

    Posted Apr 06, 2015 07:22 AM


    Hi All,

     

    Do we have any WOB to check the application end simillar to APPLEND in ESP version.



  • 2.  Re: APPLEND Workload Object in D Series

    Broadcom Employee
    Posted Apr 06, 2015 11:17 AM

    Hi,

     

    There is no explicit job to check the application end.

     

    Ravi Kiran



  • 3.  Re: APPLEND Workload Object in D Series

    Posted Apr 16, 2015 03:34 AM

    Hi Ravi,

     

    Thanks for your response.

     

    Do have any way we can achieve the result using any techinques, Java Scripts something like that ?



  • 4.  Re: APPLEND Workload Object in D Series

    Posted Apr 15, 2015 08:51 AM

    For any of our applications that are 1 flow of jobs all dep on each other we use the link at the start and end.  our DI_ODS application has a start link of DI_ODS_START and end link of DI_ODS_COMPLETE.  Our BI reporting team reports off the start and end to get the SLA/Metric information about flow on how long they ran.  We don't do this on appications that have many different standalone jobs or mini flows only flows where the entire flow is all inter dep.



  • 5.  Re: APPLEND Workload Object in D Series

    Posted Apr 16, 2015 03:33 AM

    Thanks shimaneks.

     

    But I was looking for an WOB, that will be acting as end of application, without being setting up any dependency.

     

    We have that kind of WOB in CA - ESP Edition.