Scenario
Job A has a dependency on Job B with LT=12 hours
Job B runs once successfully (rc<=4), but, then runs again unsuccessfully (rc>4) – this may happen when non mainframe applications send a file twice.
Question – does Job A think that Job B ran successfully (i.e. the first time), or unsuccessfully (2nd time). If the latter, I can easily set this up. However, if it thinks Job B ran successfully, how can I prevent Job A running?