  • 1.  How do you validate some parm changes are in effect?

    Posted Apr 12, 2018 09:54 PM

    When we change a parm in JOBTRA00 we have to show evidence that the parm is in effect. JOBTRA00 parms do not show up during the start of the address space and there is no command to display the JOBTRA00 parms that are actually in effect. This makes getting our change requests approved very difficult because we cannot prove that many of the parms that are modifiable have actually been effectuated. Especially parms that require a restart of the Jobtrac address space. Example. I need to change the MONITORDELAY parm as prescribed by CA. The PARMS command is not satisfactory as all it does is browse/edit the defined TRACPARM PDS. It is worthless as it has no bearing on what Jobtrac was initialized with. Not having this capability seems to be product deficiency.  How does one validate that certain parms are actually in effect?



  • 2.  RE: How do you validate some parm changes are in effect?
    Best Answer

    Broadcom Employee
    Posted Feb 04, 2020 09:32 AM
    There currently is not a display in Jobtrac to show the parms in effect for Jobtrac.    The PARMS command is the only comand for showing what is in JOBTRA00 but as you have indicated it is on a means of browsing/editing the JOBTRA00 member that Jobtrac uses at startup.  We welcome the opportunity for your voice to be heard regarding any
    enhancements to the product's current functionality and design.  To do this please open an entry on the Broadcom Mainframe Software Community Idea Board, for which I am providing the link below:


    https://community.broadcom.com/ideation/allideas


    Regards,
    Alisa