The Clarity documentation Fill Resource Requisitions - CA PPM - 14.2 - CA Technologies Documentation mentions that a notification is sent to both Requester and Booking Manager (both new and old) when booking manager for a particular requisition is changed - notification should go to both new and old booking manager.
But none of the parties (requester, old booking manager and new booking manager) involved are notified when a change in Booking Manager is made. Am I missing something?
The following table shows the parties that are notified when the requisition status changes:
Requisition Status Changes | Requested By | Booking Manager |
---|
Created | | |
From New to Open | Notified | Notified |
From Open to New | Notified | |
From Open to Propose | Notified | Notified |
From Proposed to Booked | Notified | Notified |
From Open to Book (if requisition approval is not required) | Notified | |
Booking Manager changes | Notified | New and old booking manager are notified. |
Requested By changes | | |
Closed | Notified | Notified |
Deleted | | |