Hi Kathryn,
Thanks for the tips !
This is a good approach for fixing few timesheets : new resource class are taken in account.
Based on your approach, I tried to create WIP adjustment (i.e. transfer on the same invest, resource and task + calculate new) then approve WIP adjustment and you obtain the same result. I believe this approach is more convenient when you have to many timesheet to fix.
Bit still have one issue : i have also changed the rôle of the resource in order to be in aligned with the resource class and new rôle is not taken in account whatever the approach.
I took care to change the rôle at the resource level, project level and task level.
Do you have any idea on how to update the financial transactions in order to update the role of the resource recorded in "old" transaction?
------------------------------
Patrick
------------------------------
Original Message:
Sent: 11-16-2019 11:17 AM
From: Kathryn Ellis
Subject: Is there a way to update the financial transactions in order to update the resource class recorded in "old" transaction?
This is a tricky situation to correct because the current design does not provide a method to directly update the field in WIP Adjustments.
The only way to do it properly (for which you might want to test on a non-prod environment first) is to do the following:
- Keeping the OLD Resource Class - Create Timesheet Adjustments to ZERO the existing transactions
- Process the adjustment all the way through to financials.
- This will create an offset record to negate the first posting.
- Then, update the Resource Class on the resource's properties
- Create a Timesheet ADJUSTMENT and ADD a NEW row for the assignment and post thru to financials
- This will create the new row with the new resource class in WIP
Original Message:
Sent: 11-15-2019 07:31 PM
From: Patrick MOYSAN
Subject: Is there a way to update the financial transactions in order to update the resource class recorded in "old" transaction?
Hi,
Is there a way to update the financial transactions in order to update the resource class recorded in "old" transaction?
Here the context:
I have done some changes at the resource level in order to be inline with the new organisation : mainly new resource class
Some timesheets were already post and financially proceeded before I have made all change on some projects.
The side effect is that in the cost plan of many projects, I see 2 times the resource with different resource class (the previous one and the new one)
I would like to have a single line per ressource but that mean I need to apply the new resource class for old financial transactions
------------------------------
Patrick
------------------------------