I have a task in which i have an assignment those etc is now 0. There are some actual recorded against this. The span for the assignment is from 1st Jan 2013 to 31st Dec 2015. But when i run the cost plan it displays that there is some planned etc still remaining in the year 2013. The loading pattern is front for this assignment.
Also when i see the PPA_WIP tables, the sum of actual is different from the value of actual in assignment table for this assignment.
How can i fix this
many thanks,
Samad Abdul Aleem