Deleted one of the project from PRODUCTION

Jump to Best Answer
  • 1.  Deleted one of the project from PRODUCTION

    Posted 30 days ago
    Hi Everyone,

    I have deleted one of the project from Production Environment. Is there a way to recover the project ?


  • 2.  RE: Deleted one of the project from PRODUCTION

    Posted 30 days ago
    Hi Arun
    You could XOG it in from another environment, or

    restore a copy of the most recent Production backup to a new database schema, link it to a test Clarity server and xog out the project from there, then xog in to Production.


  • 3.  RE: Deleted one of the project from PRODUCTION

    Posted 30 days ago
    Hi Nika,

    I am NOT able to follow whatever you mentioned


  • 4.  RE: Deleted one of the project from PRODUCTION

    Posted 29 days ago
    Are you saying you set the purge flag on and run the delete the investments job?


  • 5.  RE: Deleted one of the project from PRODUCTION

    Posted 28 days ago
    Yes Marti. I set the flag and ran the delete investment jobs.


  • 6.  RE: Deleted one of the project from PRODUCTION
    Best Answer

    Posted 28 days ago
    Then it is gone from the database and there is no way to recover it from the active system.
    As Nika says
    If you have a database backup
    set up another system and restore the backup there.
    Then XOG out the project from that restored system.
    XOG in the file to the active prod system.
    That will bring back everything that can be XOGed from the time of the backup
    If there are things that can not be XOG and you want you must manually copy them from the restored system to the active prod system.
    If you do not have a back up then that is it.
    All you can do is recreate the project from your memories and any pritented or saved reports for the date there is..


  • 7.  RE: Deleted one of the project from PRODUCTION

    Posted 27 days ago
    Thank you Marti for your detailed explanation