Clarity does not do this OOTB. A number of years ago we built our won contractor management portlets and processes. They allowed us to enter the contractors start and end date, and budget. When the contractor got within 15% of the end date or 15% remaining on the contractors contract value, it would automatically send an email to the PM stating that the contract was coming to an end. This allowed the PM's to be proactive.