  • 1.  Unable to add all my project Tasks to my timesheet in Clarity

    Posted Jul 17, 2019 12:27 AM
    ​Hi,

    One of our user's have raised an issue where he is unable to add all of he's project tasks to he's timesheets.
    We are currently running Clarity PPM 13.2 version.

    Any help on the procedure of this would be appreciated.

    Kind Regards
    Ahmet


  • 2.  RE: Unable to add all my project Tasks to my timesheet in Clarity
    Best Answer

    Broadcom Employee
    Posted Jul 17, 2019 02:27 AM
    Hi Ahmet,
    If the user is not able to view the tasks in the timesheet page, please check this thread.. 
    https://community.broadcom.com/communities/community-home/digestviewer/viewthread?MID=719636#bm8691bd04-5bf4-4cb4-9d77-2ef630adb746

    Thanks,
    Jerin


  • 3.  RE: Unable to add all my project Tasks to my timesheet in Clarity

    Posted Jul 17, 2019 04:24 PM
    ​Hi Jerrin,

    Thank you for the link, all is good now.

    Kind Regards


  • 4.  RE: Unable to add all my project Tasks to my timesheet in Clarity

    Broadcom Employee
    Posted Jul 17, 2019 08:03 PM
    Thank you Ahmet - Glad it worked for you! 

    Regards,