Hi All,
It seems the new Timesheets UX is confusing for users who work 4 hours per day when the configuration field
Display Unit is set to
Days in Administration :: Timesheet options.
Here is an example :
My resource testLeo is working 4 hours each morning from monday to friday, so he should work 20 hours per week. This is set in its calendar by configuring its shifts.
This is one of its Timesheets when
Display Unit is set to Hours :
- The TimeSheet is filled with five times 0,5 days. It could make sense and I could make it work with my users, but it's really not accurate. My user worked full days. He works 4 hours per day, but those are still technically full days.
- That 2,5/5 slider, on the other hand, can't be sold to my users. And I can't blame them : if only it displayed 2,5/2,5 it wouldn't give the impression the resource didn't work at max availability. Right now, it shows something is wrong when the TimeSheet is filled out properly.
But this isn't the worse case scenario yet. If testLeo fills its TimeSheet (naturally, with five times 1 day) when
Display Unit is set to Days, Clarity clearly implies that everything is fine :
But of couse, when I set
Display Unit to
Hours :
So I'm a bit lost here :
- Am I missing something? Did I forget to configure something ?
- If not, is it a know bug ? Is there a quick fix or patch? Is a resolution announced yet ? I searched for a while but couldn't find anything…
Thanks in advance ! Best regards,
Léo