Hi Venkitta,
One approach i can see is:
1. Go to the financial plans of the project
2. Make a copy of the Cost Plan
3. On the properties of the new cost plan, modify the plan end period to the current month
4. The planned cost of the cost plan created will be cut off till the end of this month.
Hope this helps
Original Message:
Sent: 07-20-2019 03:26 PM
From: VENKITTA SUBRAMANIAN
Subject: Planned cost till date
CA PPM Saas 15.6.1
We are using the Cost plan and Budget plan and we have a requirement to calculate the planned cost till date.
Is there any OOTB metrics available to get this value
Your help/pointer is greatly appreciated
Thanks
-Venkitta