Hi,
Do you want to trigger event after the application has completed?
Set the application property to "Wait for previous generation".
Then trigger the event five times, the last four application generation will come in Monitor but will be be on hold.
When the first generation completes, then next one will start and so on.
HTH,
Nitin Pande
------------------------------
Support
Broadcom
Toronto
------------------------------
Original Message:
Sent: 05-29-2020 04:55 AM
From: pardeep kumar
Subject: WLA Query
Hi Team,
I need to execute a particular schedule in QA 5 times back to back.(So when the first run gets completed 2nd run should get triggered).
Can we have some configuration/programming in WLA for this
Regards,
Pardeep