Need help understanding how cycle/lead team is calculated.

  • 1.  Need help understanding how cycle/lead team is calculated.

    Posted Jul 16, 2018 03:59 PM

    I am trying to explain the spike shown in week 07/08 of the Cycle Time Report.  I ran the Cycle Time Data App based on the parameters below: Discovery/Design (In Progress) to Completed (Accepted) for the week beginning 07/08.  The two Stories fitting that criteria had Cycle Times of approximately 28 and 24 days (average of 26 days).  Yet the Graph shows an average of 17.5 days.  How do I determine what data the Cycle Time Report is using to create the graph segments?



  • 2.  Re: Need help understanding how cycle/lead team is calculated.
    Best Answer

    Broadcom Employee
    Posted Jul 17, 2018 02:13 PM

    Hello David,

     

    Have you look at the following help page which gives a description of the cycle/lead time?

     

    Team Measurements | CA Agile Central Help 

     

    This should provide you with the information you are looking for. If you still have questions please let us know.

     

    Thank you,

     

    Christian