  • 1.  Release Planning/Custom Board

    Posted Aug 28, 2019 03:25 PM
    I need something like the Release Planning view under Portfolio for Multiple Projects.  Is there something I can customize like that? 

    We have multiple Projects that I need to have a view by Release then a view by Milestone.

    Cindy

    ------------------------------
    Cynthia_I_Remick@Optum.com
    ------------------------------


  • 2.  RE: Release Planning/Custom Board
    Best Answer

    Posted Sep 25, 2019 01:08 PM
    Hi Cynthia,

    If you want a separate view for each project, you could add multiple versions of the Release Planning app to a page, and in the settings point each app to a specific project scope.