Hello Team,
Submitted an Idea for the subject.
Example:
Parent Item X planned end date: 31. Dec.2019
Child Item X1 planned end date: 17 Nov 2019
Child Item X2 planned end date: 03 Nov 2019 (originally planned).
Imagine a case now: X2 planned end date is changed to 14 Jan 2019 for some reason.
Obviously, now the parent (X) planned end date is inconsistent when compared to one of it's child date.
If this inconsistent data could be flagged with a warning sign,
the parent owner can look into it and take the appropriate action as needed.
Submitted an idea:
https://community.broadcom.com/participate/ideation-home/viewidea?IdeationKey=a1bb5d29-ffc2-4e5b-bdec-ed78564f57cfLike it, if you think this is helpful for the users.
Thanks,