In my mind this would be a similar scenario to unfinished work in an iteration. Normally we would split the story and move unfinished work to it, but that isn't an (automatic) option with child stories like it is with tasks.
I'm not familiar with all the nuances of reporting, so maybe others can chime in, but I'm wondering if splitting the parent story and moving the completed stories to the [Unfinished] story would work. Then you'd be free to work on the [Continued] work in the next iteration.
Original Message:
Sent: 07-30-2019 02:08 AM
From: Nikhitha Kamath
Subject: Blocked Parent-Child User Stories
Hi !
Is there an alternative to closing a Parent User Story with blocked Child User Stories?
------------------------------
Regards,