How can I show or compare a resource's actuals versus estimates in a chart?
Are there any examples of best practice on simple resource utilization reporting?
Thanks,
Ramon
Ramon;
There seems to be something odd going on in the community forum- I never saw your question until today so I'm guessing that others didn't either. You may have already solved this but there's a Utilization Chart app in the app catalog that should address this. It requires that you use Tasks (the only measure of utilization in Agile Central is task hours) and that you set individual iteration capacities on the Team Status page. Hope that's helpful.
Eric, I think it's probably because we've been trying to mark questions as answered / assumed answered so we can focus on the new ones coming in. So, we're now seeing some of the old ones that may not have a reply yet ...