This typically happens when the named resource does not have sufficient availability to take all of the ETC that was planned for the Role.
The only way I found to correct this is to go into ARP and manually assign the remaining 0.08 hours to the named resource and set the ETC of the Role to 0.
You will then "overallocate" the names resource so it is up to you if that is what you want.
Original Message:
Sent: 05-16-2020 01:52 AM
From: Martti Kinnunen
Subject: Split ETC on Role Replacement
Do the role and the resource have the same availability?
Original Message:
Sent: 05-15-2020 04:59 PM
From: Jia En Chua
Subject: Split ETC on Role Replacement
When I tried to replace a generic role with a named resource, the role will not get replaced entirely in assignment. For example, a role has 8.00 ETC initially. After replacing it with a named resource, the ETC became 0.08 and the other 99% (7.92) is assigned to the named resource.