  • 1.  Status Report New UI

    Posted Oct 31, 2019 04:26 AM
    Hi,

    We are in Clarity 15.6.1  recently upgraded. The Status Report in the New UI provides options to select and display data.
    However, we  have seen that when we select 'Tasks' and 'Completed Tasks', not all the tasks are displayed in the Report.

    Is there any condition to display all the tasks?

    Regards,
    Divya


  • 2.  RE: Status Report New UI
    Best Answer

    Broadcom Employee
    Posted Oct 31, 2019 04:30 AM
    You need to select the Include in Status Report option for tasks that you want to display in the status report. You can review the associated documentation here.

    ------------------------------
    Clarity PPM Documentation Team
    ------------------------------