1. When I change the duration (increase) of last task of the project higher than project finish date-> Automatically the Project Finish Date Changes
That is standard behavior. The logic includes that the project cannot finish earlier than the last task.
2. When I change the duration (decrease) of last task of the project -> Project Finish Date is not Changing and it requires the auto scheduling
Typically that would mean that the effort which was scheduled for a certain period of time requires action.
The system cannot know if the effort is just reduced by the respective amount or redistributed over the new time period or what.
3. When we change the duration of a predecessor activity, neither the successor activity duration is increased or decreased nor the project finish date is not changing. It requires that we need to schedule even in critical path.
Again the system cannot know if the effort is just reduced by the respective amount or redistributed over the new time period or what. Also the system does not know when a predecessor task is shortened if all the prerequisites are there so that the successor can be started earlier.
My question is as soon as we change a task duration in critical path and without using auto- scheduling option, is it possible for system to adjust the finish date for a project.
Is it possible to write a process for that.
That is typically the job of the project manager to track the progress of the project and take action accordingly. The software or the system is not and cannot be a project manager. There are too many things to consider.
Yeas, it is possible to write a process which autoschedules the whole projecct following the autoschedule logic if the project manager cannot do that.
Original Message:
Sent: 11-04-2019 05:13 AM
From: RONALD REAGAN C P
Subject: Reg Auto Updation of schedule
Hi suman,
When I change the duration (increase) of last task of the project higher than project finish date-> Automatically the Project Finish Date Changes
When I change the duration (decrease) of last task of the project -> Project Finish Date is not Changing and it requires the auto scheduling
When we change the duration of a predecessor activity, neither the successor activity duration is increased or decreased nor the project finish date is not changing. It requires that we need to schedule even in critical path.
My question is as soon as we change a task duration in critical path and without using auto- scheduling option, is it possible for system to adjust the finish date for a project.
Is it possible to write a process for that.
Original Message:
Sent: 11-03-2019 02:32 AM
From: Suman Pramanik
Subject: Reg Auto Updation of schedule
If you open the project in gantt and add the column Duration to the selected field and update the duration your project end date should move forward. Also if you change your task finish date beyond the project finish date it should move the project finish date also
------------------------------
Thanks & Regards
Suman Pramanik
Principal Support Engineer | Customer Success & Support, Enterprise Software Division
Broadcom
Original Message:
Sent: 10-31-2019 01:55 AM
From: RONALD REAGAN C P
Subject: Reg Auto Updation of schedule
Is there any way in which if we change the task duration will it automatically change the project finish date without Autoscheduling Options.