  • 1.  Calculating Project Storyboard's "Remaining Allocation"

    Posted Apr 01, 2020 07:43 AM
    The Clarity Project Storyboard report includes a field entitled "Remaining Allocation". What is the equation used to calculate this value?

    ------------------------------
    Portfolio Analyst
    State of Michigan
    ------------------------------


  • 2.  RE: Calculating Project Storyboard's "Remaining Allocation"
    Best Answer

    Posted Apr 01, 2020 08:59 PM
    Hi Bill,

    Remaining allocation in the storyboard report internally uses a DWH function (DWH_INV_REMAINING_ALLOC_FCT) to calculate the remaining resource allocation hours on the project.

    For instance, if the allocations in the resource plan/team tab are as below with the future allocations:


    Storyboard report reflects the remaining allocation as 951.20.

    Regards,

    ------------------------------
    Praneeth Desur
    Clarity PPM Specialist
    Toyota Finance Australia
    ------------------------------



  • 3.  RE: Calculating Project Storyboard's "Remaining Allocation"

    Posted Apr 02, 2020 09:13 AM
    @praneeth.desur Excellent! That makes sense. I appreciate the information!​

    ------------------------------