Remaining allocation in the storyboard report internally uses a DWH function (DWH_INV_REMAINING_ALLOC_FCT) to calculate the remaining resource allocation hours on the project.
For instance, if the allocations in the resource plan/team tab are as below with the future allocations:
Regards,
------------------------------
Praneeth Desur
Clarity PPM Specialist
Toyota Finance Australia
------------------------------
Original Message:
Sent: 04-01-2020 07:42 AM
From: Bill Brown
Subject: Calculating Project Storyboard's "Remaining Allocation"
The Clarity Project Storyboard report includes a field entitled "Remaining Allocation". What is the equation used to calculate this value?
------------------------------
Portfolio Analyst
State of Michigan
------------------------------