    Hello,

    Tasks that have been entered in Clarity 15.3 do not display in MS Project. 
    The tasks appeared at the bottom of the Gantt in Clarity so I moved them to the correct location. They were completed tasks. It was a Summary Task plus the "work package" tasks.  Has anyone experienced this issue?

    Regards.

    Todd Bryant
    mywegmansconnect



  • 2.  RE: Tasks entered in Clarity 15.3 don't display in MS Project
    Best Answer

    Posted 11-06-2019 03:55 PM
    Hi! Todd, did you check if this summary task has a resource assigned? if so, sometimes MSP seems to be broken showing summary task in those condition, it not good practice, and gets broken, and also clarity work odd.

    If you only experience this on 1 project, perhaps is broken, in the task, and fails. With new versions, and the boards, new task moves to the button part of the list.

    Give us a feedback or some screns, cheers!
    Pablo

    ------------------------------
    [Designation]
    PPM Sr Consultant
    SAM
    [City]Argentina
    ------------------------------