can you check the attribute start and finish date API in project as per the error.
------------------------------
Thanks & Regards
Suman Pramanik
Principal Support Engineer | Customer Success & Support, Enterprise Software Division
Broadcom
------------------------------
Original Message:
Sent: 09-10-2019 04:18 PM
From: Arunachalam Angusamy
Subject: New User Experience Roadmap - Synching
Hi Everyone,
When I go to Roadmap and sync the start date and finish date for all the projects that I included in the roadmap, I am getting this below error message. Any Idea ?
API-1006 : The value 'start_date,finish_date' for Attribute '{1}' is not in expected format or is invalid