Tasks entered in Clarity 15.3 don't display in MS Project

  • 1.  Tasks entered in Clarity 15.3 don't display in MS Project

    Posted Sep 11, 2019 12:11 PM
    Tasks that have been entered in Clarity 15.3 do not display in MS Project.
    The tasks appeared at the bottom of the Gantt in Clarity so I moved them to the correct location. They were completed tasks. It was a Summary Task plus the "work package" tasks. 
    Has anyone experienced this issue?

    ------------------------------
    Sys Admin
    CPS Energy - Texas
    ------------------------------