  • 1.  Planned Cost in the Portfolio Waterlines

    Posted Nov 03, 2019 10:54 PM
    Hi All,

    Can someone explain how the 'planned costs' (by month) is calculated in the the Portfolio Waterlines. I've checked each of the investments (project, ideas) cost plan and it is not the same result in the waterlines.

    Am I missing something?

    Thanks


  • 2.  RE: Planned Cost in the Portfolio Waterlines
    Best Answer

    Posted Nov 04, 2019 03:19 AM
    Figures in the waterline view reflect the values between the portfolio start and finish. Any investment values outside those dates are not visible. 

    Regards, 

    Steve


  • 3.  RE: Planned Cost in the Portfolio Waterlines

    Posted Nov 04, 2019 04:22 PM
    Do those figures also depend on running the synch job?


  • 4.  RE: Planned Cost in the Portfolio Waterlines

    Posted Nov 04, 2019 06:29 PM
    Thanks and noted.

    What I am seeing is the below situation for particular months:

    The planned cost in the Cost Plans (of all linked projects in the hierarchy) are:
    Jan = 20K
    Feb = 20K

    However the planned cost in the Waterlines are:
    Jan = 18,788
    Feb =  20,498

    I'm trying to figure out why these planned costs are different.