Thanks and noted.
What I am seeing is the below situation for particular months:
The planned cost in the Cost Plans (of all linked projects in the hierarchy) are:
Jan = 20K
Feb = 20K
However the planned cost in the Waterlines are:
Jan = 18,788
Feb = 20,498
I'm trying to figure out why these planned costs are different.
Original Message:
Sent: 11-04-2019 03:19 AM
From: Steve Robinson
Subject: Planned Cost in the Portfolio Waterlines
Figures in the waterline view reflect the values between the portfolio start and finish. Any investment values outside those dates are not visible.
Regards,
Steve
Original Message:
Sent: 11-03-2019 10:54 PM
From: Thomas Tran
Subject: Planned Cost in the Portfolio Waterlines
Hi All,
Can someone explain how the 'planned costs' (by month) is calculated in the the Portfolio Waterlines. I've checked each of the investments (project, ideas) cost plan and it is not the same result in the waterlines.
Am I missing something?
Thanks