I am trying to figure out how the value of the Project Storyboard report's "Baseline" (in the Labor Hours section) is derived. I have been told that it is the number of posted hours at the time of the most recent baseline. However, it is almost always a larger value than the Actuals (in the same section). Therefore, what I have been told must be wrong.
The field is base_total_hours (from the dwh_inv_summary_facts table). What values does this field really contain?
------------------------------
Portfolio Analyst
State of Michigan
------------------------------