Hi there, did you check in settings of the project the % Complete Calculation?
There are 3 options, Duration, Manual & Effort. If you have it on Manual you have to do it by your self, in the other options the % complete of the task moves and increase the % of the summary/phase tasks!
cheers!
Pablo
------------------------------
[Designation]
PPM Sr Consultant
SAM
[City]Argentina
------------------------------
Original Message:
Sent: 12-06-2019 08:52 AM
From: VENKITTA SUBRAMANIAN
Subject: Phase/Summary percent complete and status issue
CA PPM SaaS version 15.6.1
On the Tasks->PPM Gantt page, when all the tasks underneath the phase/summary is updated to 100% the phase is still showing up 0% and Not Started status
Is this expected behavior? The expectation from the user was that, when all the tasks are complete within the phase then phase status should be updated automatically
Any pointer/reference to community forum is greatly appreciated
Thanks
Venkitta