Clarity

 View Only
  • 1.  Phase/Summary percent complete and status issue

    Posted Dec 06, 2019 08:53 AM
    CA PPM SaaS version 15.6.1

    On the Tasks->PPM Gantt page, when all the tasks underneath the phase/summary is updated to 100%  the phase is still showing up 0% and Not Started status

    Is this expected behavior?  The expectation from the user was that, when all the tasks are complete within the phase then phase status should be updated automatically

    Any pointer/reference to community forum is greatly appreciated

    Thanks
    Venkitta


  • 2.  RE: Phase/Summary percent complete and status issue

    Posted Dec 09, 2019 08:31 AM
    Hi there, did you check in settings of the project the % Complete Calculation?
     
    There are 3 options, Duration, Manual & Effort. If you have it on Manual you have to do it by your self, in the other options the % complete of the task moves and increase the % of the summary/phase tasks!
    cheers!
    Pablo

    ------------------------------
    [Designation]
    PPM Sr Consultant
    SAM
    [City]Argentina
    ------------------------------



  • 3.  RE: Phase/Summary percent complete and status issue
    Best Answer

    Posted Dec 10, 2019 02:02 AM
    I am wondering if the 'Update % Complete' job impacts just the Investment or also the Phases on the Investment. We have got this scheduled to run throughout the day, and I know that it does true-up the Investment's % Complete calculation.

    Cheers,
    Will


  • 4.  RE: Phase/Summary percent complete and status issue

    Posted Dec 10, 2019 02:43 AM
    Thanks.  It worked.


  • 5.  RE: Phase/Summary percent complete and status issue

    Posted Dec 10, 2019 02:45 AM
    Thanks everyone for the response.  Appreciated.