  • 1.  FTE calculation

    Posted Apr 03, 2020 10:12 AM
    Clarity PPM 15.6.1 ( SaaS)

    We have resources working with different daily availability rate.   Ex: India based resources at 8 hours per day and UK based resource work at 7.20 hours / per day and some other countries with 7.50 hours per day.

    All of the resources are aligned to Standard calendar (default).

    When I changed the Unit of Measure from Hours to FTE, it is showing less than 1 FTE for the daily availability less than 8 hours  and the FTE is showing more than 1 when the availability is 9 hours per day

    Please let me know how the FTE is calculated?  Is it always 8 hours regardless of the resource calendar?  Do I have to maintain different calendars for each availability rate like 7.2, 7.5, 9 hours?

    Any help/pointer is greatly appreciated

    Thanks
    -Venkitta


  • 2.  RE: FTE calculation
    Best Answer

    Broadcom Employee
    Posted Apr 03, 2020 10:17 AM
    Hi Venkitta,
    Please see:
    How is FTE calculated:
    https://knowledge.broadcom.com/external/article?articleId=29080

    An explanation to your scenario:
    https://knowledge.broadcom.com/external/article?articleId=35295

    Regards
    Joxi


  • 3.  RE: FTE calculation

    Posted Apr 03, 2020 10:37 AM
    Thanks Joxi for the quick response

    I did go through the links but how do I get 1 FTE for resources with 7.20 hours availability per day?


  • 4.  RE: FTE calculation

    Broadcom Employee
    Posted Apr 03, 2020 10:42 AM
    HI Venkitta,
    What are the shifts of the calendar set as Standard Calendar?
    Only 1 can be set as Standard.
    1 FTE will be calculated for the resources whose shifts are aligned with the one marked as Standard
    Regards
    Joxi


  • 5.  RE: FTE calculation

    Posted Apr 03, 2020 11:08 AM
    Standard Calendar
    We have 8 hour shift