  • 1.  Allocated hours automatically getting updated on Project team tab for resource

    Posted Nov 07, 2019 01:27 PM
    Can someone please explain the scenario when allocated hours of a resource automatically get updated on team tab. If suppose a resource has 10 allocated hours on project team tab, it get updated to 11 suddenly. What kind of changes on either a resource  (like change in finish date) or task would update allocated hours automatically?


  • 2.  RE: Allocated hours automatically getting updated on Project team tab for resource

    Broadcom Employee
    Posted Nov 07, 2019 10:45 PM
    Hi Sravani, 

    There are few jobs as I mentioned below which can change the allocation and assignment start and finish dates in the TEAM tab. In the TEAM tab, you can also see an option called "Allocate from Estimates". When clicked that action, it updates the team record(s) as per the Assignment in the Tasks. 


    You can find more details in the Product Documentation also. Have a look. 


    ------------------------------
    Abhisek Dhar
    Senior Engineer
    Clarity PPM Support
    ------------------------------



  • 3.  RE: Allocated hours automatically getting updated on Project team tab for resource
    Best Answer

    Broadcom Employee
    Posted Nov 08, 2019 09:51 AM
    Another possiblity,
    If the Allocation Start / Finish dates are null, it uses the investment's Start / Finish Dates and thus could automatically change the total amount of allocations when the dates of the investment are extended.