Hi All,
We have observing a strange issue with respect to dates in Clarity.
The Process finish dates are showing as less than its start date. This is not consistent for all the process but can be seen for every other process.
Also dates updated through XOG are also showing dates less than the actual timestamp.
Could you please help to solve the issue.
Thanks,
Pragya Singh