Clarity

 View Only
  • 1.  Couldn't find Project '% Complete' in DWH tables

    Posted Sep 10, 2020 04:01 AM
    Edited by Jeevana Battu Sep 10, 2020 04:01 AM
    Hi,

    I couldn't find Project '% Complete' in DWH tables, even could not able to select '% complete ' field in Project object to copy it in DWH tables.

    Please help on getting this field in DWH tables for reporting purpose.

    Thanks,
    Jeevana.


  • 2.  RE: Couldn't find Project '% Complete' in DWH tables

    Posted Sep 10, 2020 12:30 PM

    Interesting to hear the official explanation.
    There must be a reason why it cannot be selected for DWH.

    As a project can have any of the three optional calculation methods it is quite unpredictable when the value will be updated for a given project. 
    So not a good candidate for precise reporting.




  • 3.  RE: Couldn't find Project '% Complete' in DWH tables
    Best Answer

    Broadcom Employee
    Posted Sep 10, 2020 01:16 PM
    Hi Jeevana

    Some fields cannot be selected for DWH because they are already included.

    % Complete is added on Task Object : 


    To get the Project values you may just have to aggregate them in your report.

    Hope this helps -Nika

    ------------------------------
    Nika Hadzhikidi
    Sr Principal Support Engineer
    Broadcom
    ------------------------------



  • 4.  RE: Couldn't find Project '% Complete' in DWH tables

    Posted Sep 11, 2020 03:24 AM
    Thanks Nika, this is helpful.