Clarity

 View Only
  • 1.  Any way to change task finish date without actually changing ETC

    Posted Oct 05, 2020 04:24 AM
    Hi All,

    I would like to know if we can anyway change the Task Finish date of past dates without even changing the ETC value?

    Kindly suggest anyway if clarity has any other functionality.

    Regards
    Vinay


  • 2.  RE: Any way to change task finish date without actually changing ETC

    Posted Oct 05, 2020 05:15 AM
    Change the task to fixed duration.


  • 3.  RE: Any way to change task finish date without actually changing ETC

    Posted Oct 05, 2020 05:20 AM
    There is some discussion about this in
    https://community.broadcom.com/enterprisesoftware/communities/community-home/digestviewer/viewthread?MessageKey=c7ddc139-e86c-4b97-ba45-51ab4d24fe2f&CommunityKey=7f0cbca3-5f93-4d44-a369-1a8ce98f5578&tab=digestviewer#bmc7ddc139-e86c-4b97-ba45-51ab4d24fe2f


  • 4.  RE: Any way to change task finish date without actually changing ETC

    Posted Oct 05, 2020 06:18 AM
    Hi Martti,

    Thank you for your response. DOes making FIxed duration have any impact on the existing functionality in the specific project . What needs to be kept in mind before we make it fin=xed duration task. Any further change in the finish date can be made?

    Thank you
    Vinay


  • 5.  RE: Any way to change task finish date without actually changing ETC

    Posted Oct 05, 2020 07:30 AM

    That usually keeps the task from being autoscheduled and relies on the project manager manually settingthe schedule:

    I am not sure what happens to the ETC if actuals are not entered as planned. (Also see fixed loading pattern). 

    See
    https://techdocs.broadcom.com/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-premise/15-8-1/Using-Classic-Clarity-PPM/project-management/owb-manage-projects-with-open-workbench/owb-add-project-tasks-and-assign-resources.html

    https://techdocs.broadcom.com/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-premise/15-8-1/Using-Classic-Clarity-PPM/project-management/owb-manage-projects-with-open-workbench/owb-schedule-projects-in-open-workbench/autoschedule-projects-in-open-workbench.html