  • 1.  Timesheet Effort Gauge

    Posted Dec 28, 2021 02:12 PM
    Hello All,

    I want to know how Timesheet Effort gauge is displaying data, i have few users who are available for 7.5 hours a day so their total time for a week is 37.5 hours but the gauge is displaying 39 hours.

    I have checked the availability  rate it is 7.5 hours.

    Thanks
    Pavithra

    =====-----=====-----=====
    Notice: The information contained in this e-mail
    message and/or attachments to it may contain
    confidential or privileged information. If you are
    not the intended recipient, any dissemination, use,
    review, distribution, printing or copying of the
    information contained in this e-mail message
    and/or attachments to it are strictly prohibited. If
    you have received this communication in error,
    please notify us by reply e-mail or telephone and
    immediately and permanently delete the message
    and any attachments. Thank you



  • 2.  RE: Timesheet Effort Gauge

    Broadcom Employee
    Posted Dec 29, 2021 09:04 AM
    At one time the timesheet available hours only used the standard calendar.  In addition there were some changes to how the resource calendar calculates for the timesheet gauge.

    This has been fixed in recent versions and should reflect the resource's calendar.

    MUX Timesheet available hours only use Standard calendar

    If you are on a version of 15.9.3 patch 2 or higher it should be reflecting correctly.
    One other thing to check is that time slices are working correctly.

    If still having an issue please open a support case.



    ------------------------------
    Liz Williamson
    Principal Support Engineer - Clarity
    Broadcom
    ------------------------------



  • 3.  RE: Timesheet Effort Gauge

    Posted Jan 13, 2022 11:55 AM
    https://knowledge.broadcom.com/external/article?articleId=224422