Hello,
As you know, The total cost in cost plan is the total unit * the rate of the resource.
My issue : Our resources can move from Financial department to other one and so the Rate is updated.
My total cost in cost plan is in this case updated for in the past and so we are not able to have the real cost of the project.
For example : A project has been done in 2018 and has one resource. Total unit done for this project is 10 days
This resource was on deparment DEP1 with a rate = 100 euros by days
in 2019, resource is now on department DEP2 with a rate = 200 euros by days
In my cost plan for 2018 :
Total cost = 200*10 => 2000 euros
Actual Cost = 100*10 = 1000 euros
remaining cost = - 1000 euros
Total Unit = 10 days
Actuals unit = 10 days
Remaining unit = 0
How can I have the good cost for my project ? I would to see cost = 1000 euros
Thanks for your help
------------------------------