Hi Marius,
Calendar shifts drives the Resource Availability on the New UX timesheet. First, update the shift on the Calendar assigned to the resource and then update the daily availability on the resource profile.
------------------------------
Thanks & Regards,
Madhur Sachdeva
------------------------------
Original Message:
Sent: 07-02-2020 10:21 AM
From: Marius Nitu
Subject: Resource Availability in New UX Timesheet
Hello,
We have the following problem:
- We have a resource that used to work 8 hours per day. The timesheets in New UX showed a number of hours/40.00.
- We modified the resource availability in Classic UI from 8.00 to 6.00. The timesheets in New UX continue to show a number of hours/40.00.
Isn't the number 40.00 in New UX supposed to represent the resource availability during the selected time entry period?
Is there a job we need to run to update the number?
Thank you very much!
Marius