  • 1.  Cant edit allocation information for a project in open workbench

    Posted Jul 28, 2020 07:28 AM
    Cant edit allocation information for a project in open workbench
    Whenever we try to adjust allocation information for the project using Open Work Bench, we encounter an issue that we can't edit allocations within OWB. Our changes get automatically reverted.
    please let us know what reason could it be?


  • 2.  RE: Cant edit allocation information for a project in open workbench

    Posted Jul 28, 2020 03:28 PM
    What rights does the user have?
    Hard or soft allocation?
    Which view are you looking at in Clarity?
    Which fields are you editing in OWB?
    Which Clarity version?


  • 3.  RE: Cant edit allocation information for a project in open workbench
    Best Answer

    Broadcom Employee
    Posted Jul 31, 2020 04:11 AM
    This is happening with master/subproject structures.
    If subprojects exist you can not edit team allocation data.
    https://knowledge.broadcom.com/external/article?articleId=196338