Hi Everyone
I have been doing PPM and micro soft project integration i can save, from MS project into PPM and it creates a new project.
The concern is
I want to have an Project in PPM with tasks and then save another project / schedule into this project from MS Project
so when I view this project in PPM it should list both new and old task.
Or I have a project in MS project that have a sub project how can I save this project into PPM
I have tried saving a project into PPM from MS Project that have a sub-project it saves but it does not list/ save the tasks of the sub-project
it only takes the sub project name and make it a task in PPM.
Images bellow
MS project
PPM