Adding a Schedule from Microsoft Project into an existing project in PPM

  • 1.  Adding a Schedule from Microsoft Project into an existing project in PPM

    Posted Jul 03, 2019 08:42 AM
    Hi Everyone

    I have been doing PPM and micro soft project integration i can save, from MS project into PPM and it creates a new project.

    The concern is 
    I want to have an Project in PPM with tasks  and then save another project / schedule into this project from MS Project
    so when I view this project in PPM it should list both new and old task.
    Or I have a project in MS project that have a sub project how can I save this project into PPM

    I have tried saving a project into PPM from MS Project that have a sub-project  it saves but it does not list/ save the tasks of the sub-project
    it only takes the sub project name and make it a task in PPM.

    Images bellow
    MS project

    Project with a subjprojectPPM


  • 2.  RE: Adding a Schedule from Microsoft Project into an existing project in PPM
    Best Answer

    Posted Jul 03, 2019 01:57 PM
    That is the normal display.
    The task list does not differentiate between tasks and subprojects in how they are displayed.
    The tasks of the subproject are not displayed in the task list of the master project.

    If you go to the subprojects subpage you can see if that is a subproject


    In the PPM Gantt subprojects are displayed diferently from normal tasks

    In PPM Gantt you can also see if the tasks are loaded by clicking the + to expand