Process Update Criteria testing Dates for empty

  • 1.  Process Update Criteria testing Dates for empty

    Posted Sep 21, 2021 02:46 PM
    Hi All,
    I am trying to start a process based on an update to the Task Baseline and set a field ONLY the first time.

    My current Update criteria start is:
    ( ( Task Baseline Finish != Task Baseline Finish [Previous Value] ) and ( Task First Baseline Finish (TRG) = null ) )

    The problem is when I do create a baseline for the task, it does not start.

    Do you have any recommendations on how to test for an empty date? And how to test for a Baseline creation to start a process?