Change 1 date and have it cascade to more than just one project?

  • 1.  Change 1 date and have it cascade to more than just one project?

    Posted Jun 08, 2020 10:38 AM

    Hello!

    Do you know if there's any way in PPM to change a Customer Event date, and have it cascade to more than just one project?

     

    Example:

    Let's say there's a Vehicle X.

    And let's say PPM has separate Projects for 10 products all on Vehicle X ……

    And let's say the customer timing for Vehicle X gets delayed 2 months, meaning all 8 of their Milestone dates (Vehicle builds, etc) need to move ….

    Is there any way to change those dates in one place, and it have impact all the schedules, as opposed to having to go into all 10 projects and change 8 dates in each??

     



  • 2.  RE: Change 1 date and have it cascade to more than just one project?
    Best Answer

    Broadcom Employee
    Posted Jun 23, 2020 07:32 AM
    Hi Ihsin,
    If you have a hierarchy / structure between all those projects, then moving the start date of 1 would have an effect on the other ones.
    Date changes on a member of the hierarchy will have effects on others.
    If you have project/task dependencies, autoscheduling a given project should reschedule the structure
    Hope it helps