Hi Abhash,
Is the resource hard booked on the Team? If so, can you check if they have explicit start and finish dates on their team record? In other words, do they have dates populated here:
Original Message:
Sent: 05-29-2020 04:11 PM
From: Abhash Katakwar
Subject: Project team Allocation start date and Finish date - Auto update
Hi All, Any idea on this!!
Original Message:
Sent: 05-28-2020 06:07 PM
From: Abhash Katakwar
Subject: Project team Allocation start date and Finish date - Auto update
Hi All,
Are there any reason why resource allocation start date and finish date are auto populated with Hard allocation start date and Hard allocation finish date? Earlier, resource allocation start and finish date were same as project start date and end date, however, these dates are automatically updated to Hard allocation start date and Hard allocation finish date.