Clarity

 View Only

Financial Forecast Review by Investment

  • 1.  Financial Forecast Review by Investment

    Posted May 15, 2020 02:40 PM
    I am creating an ad hoc view report where I am needing to add the field Forecast (calculated) that is currently on the Financial Forecast Review by Investment.  Forecast (calculated) is the actual cost posted through the prior fiscal period + the planned cost beginning in the current fiscal period.

    Where do I find the actual cost posted through the prior fiscal period and the planned cost beginning in the current fiscal period?