  • 1.  Clarity Ad Hoc View Only Showing Data to 2021

    Posted May 21, 2020 06:32 AM
    Hello,

    I've created an ad hoc view using the Project Management domain on Clarity. I want to show resource allocation by fiscal month in a Crosstab. I'm using the below values:

                                                                                                                                     Fiscal Month Start Date (grouped by month).     
    Project             Resource Name          Project Role        Team Alllocation Hours

    but when I display this view without filters the allocation column stops at November 2021. We have allocation data up to 2023 in Clarity - is there a way to include this in the view?

    Thanks in advance for any advice! 
    Sarah


  • 2.  RE: Clarity Ad Hoc View Only Showing Data to 2021
    Best Answer

    Broadcom Employee
    Posted May 22, 2020 02:02 PM
    the data depends on number of periods as well as the time slice settings, i would start to review the slice dates and check for data in DWH schema

    ------------------------------
    Thanks & Regards
    Suman Pramanik
    Sr. Principal Support Engineer | Customer Success & Support, Enterprise Software Division