The sort is actually sorting all projects by their actual hours. In these with zero, they should have a number because it's available when you go into the project itself. It's almost like it's not updating the project level even though the lower levels have the information.
Actuals sum for labor resources shows up as a 0 too :(
Original Message:
Sent: 02-22-2021 01:17 PM
From: Keri Taylor
Subject: Project Grid Shows Zero Hours for Actuals
Interesting... I see a sort, have you tried sorting on the Actuals field again? Can you add actuals sum for labor resources?
Original Message:
Sent: 02-22-2021 12:30 PM
From: John Kusar
Subject: Project Grid Shows Zero Hours for Actuals
Hi Keri,
Sure - it's on the Modern Ux.
Like I said, if you look inside the project at tasks or assignments or staff, you can see Actuals posted. Just not out in this project grid.
Thanks,
John
Original Message:
Sent: 02-22-2021 12:13 PM
From: Keri Taylor
Subject: Project Grid Shows Zero Hours for Actuals
Hi John,
It would be helpful to know exactly what project grid you are referring to?
Original Message:
Sent: 02-22-2021 09:01 AM
From: John Kusar
Subject: Project Grid Shows Zero Hours for Actuals
Hello
Tasks, Assignments and Advanced Reporting all show Actuals for a given project. Any ideas on why this would be zero in the Project Grid?
Thanks,
John