  • 1.  integrating Microsoft project with PPM

    Posted Feb 12, 2020 03:53 AM
    Hi

    I have an existing schedule in Microsoft Project I want to upload it into a PPM project .
    I have install the plug in 
    made settings in MS Project  and in PPM settings PPM Version 15.5.1

    When I upload the schedule into PPM it is uploaded successfully 
    the issue happens when I open it back to MSP
    the total number of day on the duration increases and some dates are underlined with red 

    If I may ask if any one knows how to fix this

    The schedule in MSP (original)
    some Items are not auto scheduled 
    Example 
    - Task one Auto Scheduled
              - task two auto Scheduled
                     
    task three not auto scheduled
                     task four not auto scheduled

    If I change the date on task three and four it affect the duration and finish date in task two
    then duration and finish date on task one also changes to match the changes done on the lower tasks




  • 2.  RE: integrating Microsoft project with PPM

    Posted Feb 12, 2020 04:00 AM
    when I check the Schedule in PPM it looks fine with the correct dates and duration
     just wish to know if there is a setting that makes the schedule to change


  • 3.  RE: integrating Microsoft project with PPM

    Broadcom Employee
    Posted Feb 12, 2020 04:26 AM
    The scenario you describe is that tasks one and two are "summary" tasks and they should display the start date as the earliest of the start dates of its subtasks, and the finish date as the latest of the finish dates of its subtasks.


  • 4.  RE: integrating Microsoft project with PPM

    Posted Feb 12, 2020 04:35 AM
    MSP



  • 5.  RE: integrating Microsoft project with PPM

    Posted Feb 12, 2020 04:52 AM
    Just uploaded a picture for the schedule 
    the start date of the summary task is the start date of the first task 
    and the finish date of the summary task is the finish date of the last task

    new picture



  • 6.  RE: integrating Microsoft project with PPM
    Best Answer

    Broadcom Employee
    Posted Feb 12, 2020 09:03 AM
    That's right, this behaviour is expected as the summary task is "summarizing" the values from its substasks and therefore, it adjusts the dates. The parent task dates should extend to the dates of the subtasks.


  • 7.  RE: integrating Microsoft project with PPM

    Posted Feb 13, 2020 03:43 AM
    Thank you Marc
    a. Just wish to know if Auto scheduling all the task before uploading can resolve this issue 
    because I do have other schedules are done almost the same as this one they do not have any issues I think it is because some Items are auto Scheduled 
    b. I have also noticed that  the existing Schedule when It counts number of days it starts same day while when it is back from PPM it starts the next day 
    example 
    before uploading 
    duration  - 5 days  start date Monday  - finish date Friday 

    after  uploading to PPM and viewing it in MSP again 
    duration  - 5 days start date Monday  - finish date Monday following week

    is there any setting I can do in PPM or in MSP that can make sure these calculation are the same
    Cause I noticed if I change the duration from 5 to 4 days MSP does not Complain


  • 8.  RE: integrating Microsoft project with PPM

    Posted Feb 17, 2020 01:35 AM
    hi any one who knows this?


  • 9.  RE: integrating Microsoft project with PPM

    Posted Feb 17, 2020 04:39 AM
    Not answering your question, but you might benefit from reading
    MSP | Ongoing Use Tips & Tricks - RegoU 2018
    http://regoxchange.com/show/1324/

    There are also older community threads on MSP usage like
    https://community.broadcom.com/enterprisesoftware/communities/community-home/digestviewer/viewthread?GroupId=1747&MID=725203&CommunityKey=7f0cbca3-5f93-4d44-a369-1a8ce98f5578&tab=digestviewer