Hi
I have an existing schedule in Microsoft Project I want to upload it into a PPM project .
I have install the plug in
made settings in MS Project and in PPM settings PPM Version 15.5.1
When I upload the schedule into PPM it is uploaded successfully
the issue happens when I open it back to MSP
the total number of day on the duration increases and some dates are underlined with red
If I may ask if any one knows how to fix this
The schedule in MSP (original)
some Items are not auto scheduled
Example
- Task one Auto Scheduled
- task two auto Scheduled
task three not auto scheduled
task four not auto scheduled
If I change the date on task three and four it affect the duration and finish date in task two
then duration and finish date on task one also changes to match the changes done on the lower tasks